On July 23, Sinoma (Suzhou) Construction Co., Ltd. and China Africa Building Material NIG SA signed EPC Contract of 3000t/d Clinker Cement Production Line in Niger. The signing ceremony was held in Kunshan, Jiangsu province, China. Mr. Ru Changyu, Chairman of China Africa Building Material NIG SA, Mr. Lin Zhong, Deputy Secretary of the Party Committee and General Manager of Sinoma(Suzhou), the leadership team of Sinoma(Suzhou) in Kunshan and relevant personnel from both parties attended the signing ceremony.China Africa Building Material NIG SA 3000t/d Clinker Cement Production Line project is located in Keita, Tahoua, Niger. The scope of the Contract covers engineering design, equipment and material procurement, equipment supervision and transportation, construction works, installation wo...
发布时间: 2021 - 07 - 26
浏览次数:16
On December 16th, 2017, the  new dry 4500t/d clinker production line I invested by Huarun cement(Hepu) Co., Ltd  which was constructed and undertaken by Sinoma(suzhou) was successfully ignited and put into production.
发布时间: 2017 - 12 - 22
浏览次数:108
On Nov. 24th, 2017, PT. Sinoma Engineering Indonesia signed technical service contract for BAYAH 10000tpd cement production line with PT. Cemindo Gemilang in GAMA group. The work content includes production technical service from raw material reclaiming to clinker storage as well as staff training.At the signing ceremony, Mr. Ganda, the chairman of GAMA group, and Mr. Tony Liu, their general manager, praised highly of our positive working attitude and serious work style, and highly appreciated our excellent skill level. They expressed the wish of strengthening mutual cooperation of Indonesia l...
发布时间: 2017 - 12 - 11
浏览次数:474
On November 14th, PT SINOMA Engineering Indonesia, which is Sinoma’s subsidiary company in Indonesia, signed a civil construction agreement of Sulbagut Coal Fired Power Plant with Shanghai Electric Power Construction Co., Ltd(Indonesia)(hereafter referred as SEPCC) in Jakarta.This project is Sinoma(Suzhou)’s second cooperation with SEPCC. During the first cooperation(Medan 2*150MW coal fired power plant), SEPCC spoke highly of Sinoma(Suzhou), and expressed the hope that both parties could reach a strategic cooperation agreement to give full play to the advantages of both parties and complement...
发布时间: 2017 - 11 - 28
浏览次数:367
On November 6th, 2017, Long Son Line II 6000t/d clinker cement production line together with 7MW waste heat power plant was issued PAC certificate after passing performance test successfully with all indices achieving contract requirements. According to work period specified in contract, clinker shall be produced in 17 months, cement in 18 months, performance test in 21 months and waste heat generating in 23 months. The work period was calculated from May 25th, 2016, and the first successful ignition was on August 16th, 2017 under joint efforts from project management team and all construction...
发布时间: 2017 - 11 - 21
浏览次数:146
Consulate-Genral of the People’s Republic of China in Lagos, Mr. Chao Xiaoliang visited our Oil Refinery Plant Project in Nigeria, accompanied by Mr. Wang Yi, Chairman of NJZC International Construction Co., Ltd(Subsidiary company of Sinoma International Nanjing Engineering Co., Ltd, General Manager of NJZC International Construction Co., Ltd, Mr. Qiao Qiufeng, Project Manager of Oil Refinery Plant Project.Mr. Wang Yi reported the entire allocation poposed as per “the Belt and Road”and we were positively expanding Nigeria market. Mr. Qiao Qiufeng, the Project Manager detailed introduced the ma...
发布时间: 2017 - 11 - 13
浏览次数:405
To enrich the spare-time cultural life of staff and release their stress, during National Day holiday, Ethiopia branch office organized a series of recreational activities such as basketball, pingpong, badminton, chest playing etc. All staff participate enthusiastically and vigorously, the activity of which improves team-work and strengthens the sense of togetherness and inspires their passion for work, thus create a favorable atmosphere for completing all work tasks.Meanwhile, the 20th China Medical Team in Ethiopia visited the site and brought medical devices to the project department and pr...
发布时间: 2017 - 10 - 27
浏览次数:103
The as-built ignition celebration of Vietnam Thanh Thang 6000TPD cement plant line II EPC project undertaken by our company was performed at the local time 7:00 a.m. on July 2, 2017.  Many governmental personnel, Vietnam vice-primer Zheng Tingyong, director of central government office Mei Jinyong, environment minister Chen Honghe, deputy minister of public security Fei Wencheng, deputy minister of ministry of construction Fei Fanqing and Deng Chennan, etc. were invited to participate this celebration. Chairman of Thanh Thang Group Du Wenjin held this ignition celebration which was witnes...
发布时间: 2017 - 07 - 04
浏览次数:226
On June 15, 2017, Provisional Acceptance Certificate was issued by Owner, Dangote Group for the EPC project of Nigeria Ibese 3&4 clinker cement production line undertaken by Sinoma International (Nanjing).  The capacity of Ibese 3&4 is two 6000tpd clinker production lines which is the biggest output with the most advanced equipment of single cement project in Africa up to now, and is also the largest project of contract price undertaken by Sinoma International (Nanjing).
发布时间: 2017 - 06 - 29
浏览次数:340
On June 15, 2017, Provisional Acceptance Certificate was issued by Owner, Dangote Group for the EPC project of Tanzania 6000t/d clinker cement production line undertaken by Sinoma International (Nanjing).
发布时间: 2017 - 06 - 27
浏览次数:330
On June 15, 2017, Final Acceptance Certificate was issued by Owner, Dangote Group for the EPC project of Nigeria Obajana line4 6000t/d clinker cement production line undertaken by Sinoma International (Nanjing).  This project started in April, 2012, ignited in July, 2014 and got the PAC in May, 2016. In the process of project construction, the project team has overcome many difficulties like the complicated geological structure, the narrow plant area, the hot and dry weather in dry season, mosquitoes plague in rainy season, lack of material at local market, serious security situation and ...
发布时间: 2017 - 06 - 23
浏览次数:294
According to the relevant requirements of the first quarter production safety inspection, our inspection team led by leadership made the safety inspection for all overseas branches and projects site.   On Nigeria local time April 12, General Manager of Sinoma (Suzhou), Mr. Lin Zhong visited the Nigeria IBESE 3 & 4 projects for safety production inspection. Mr. Lin Zhong already got the information of the current construction situation, the existing difficulties and the solutions reported by director and general manager of Nigeria branch, Mr. Wang Yi and Mr. Jiang Wei before the i...
发布时间: 2017 - 05 - 23
浏览次数:137
On 9:08 AM, Jan. 14th, 2017, there came the final closure of rotary kiln for Vietnam Long Son phase II 6000t/d clinker cement production line which was undertaken by Sinoma(suzhou).
发布时间: 2017 - 05 - 23
浏览次数:112